August 24, 2014
August 24, 2014
Highway 99W at Thomes Creek Bridge
Construction included a 609 foot long, five-span, cast in place post tensioned concrete box girder bridge and 475 linear feet of asphalt concrete roadway. The work included removal of existing bridge, piers and abutments.
Completion date: April 25, 2019